Work on the new Ballycastle Leisure Centre has moved into its next phase, with the £16.4million development now progressing through its internal fit-out.
The seaside leisure centre project, being delivered by Co Down-based construction firm Graham, is on schedule for completion in April 2027.
After 18 months on site, construction has now moved to mechanical and electrical installations, internal partitions and flooring.
Significant work is also continuing outside the main building, with construction of the inclusive playpark under way, the car park progressing and the pump track nearing completion.
The development is being funded through investment from Causeway Coast and Glens Borough Council alongside significant support from the UK Government.
Mayor of Causeway Coast and Glens, councillor Dawn Huggins, visited the site to view progress and receive an update on the works.
Alan McCullough, project manager at Graham, said: "Welcoming the Mayor of Causeway Coast and Glens, Councillor Dawn Huggins, to the Ballycastle Leisure Centre development was a great moment for us.
"After 18 months on site, the development is really taking shape, with the internal fit-out under way and continued progress on the playpark, car park and pump track outside.
“Beyond the facilities themselves, this building is being delivered to a net zero standard, with on-site renewable technology including solar panels and heat pumps, meaning Ballycastle will get a leisure centre that's as sustainable to run as it is enjoyable to use.
"We have a strong track record of working closely with Councils and communities to deliver facilities that are genuinely needed and well used, and we're proud to be bringing that experience to Ballycastle as we move the development into its next stage."
Mayor Huggins said the project represented a significant investment in the area and would provide modern facilities for residents, community groups and visitors.
She said: "It was a pleasure to visit the new Ballycastle Leisure Centre and see the excellent progress that has been made since construction began. It is exciting to see this significant investment taking shape, and to witness first-hand how the project is progressing.
"Once complete, the new leisure centre will provide modern, high-quality facilities that will benefit residents, community groups and visitors alike. It will play an important role in supporting healthier, more active lifestyles while creating a welcoming space for people of all ages to enjoy for years to come."
The facilities consist of a 25m swimming pool (4 lane), gym, large studio, health suite, changing, reception/office, splash area and modest spa features, food dispensing/vending area, changing places facility, bouldering wall, outdoor pump track, off-road running/walking trail and accessible play park.
The project is expected to provide a new leisure and community facility serving Ballycastle and the wider area, alongside the outdoor amenities being developed as part of the scheme.

1. Ballycastle
Work on the new Ballycastle Leisure Centre has moved into its next phase, with the £16.4million development now progressing through its internal fit-out Photo: u

2. Ballycastle
Alan McCullough, project manager at Graham, councillor Dawn Huggins, Mayor of Causeway Coast and Glens, Jake Mailey, Capital Projects Officer at Causeway Coast and Glens Borough Council and Brian Tohill, general manager (Sport & Wellbeing), during a visit to the new Ballycastle Leisure Centre Photo: u

3. Ballycastle
Work on the new Ballycastle Leisure Centre has moved into its next phase, with the £16.4million development now progressing through its internal fit-out Photo: u

4. Ballycastle
Mayor of Causeway Coast and Glens, councillor Dawn Huggins, and Alan McCullough, project manager at Graham, beside the artwork created by local pupils and displayed on the Ballycastle Leisure Centre hoarding Photo: u