Time taken for planning applications in Northern Ireland is criticised in new report

Major planning applications in Northern Ireland are taking too long to process, a new report has found.
Planning applications for construction projects in Northern Ireland take too long to process says new report.Planning applications for construction projects in Northern Ireland take too long to process says new report.
Planning applications for construction projects in Northern Ireland take too long to process says new report.

The report by Comptroller and Auditor General Kieran Donnelly and Local Government Auditor Colette Kane said the planning process is not working efficiently and warned that there is “significant silo” in the system.

Mr Donnelly and Mrs Kane considered how the system has operated since April 2015, when responsibility for delivering the majority of operational planning functions passed from central government to local councils.

Hide Ad
Hide Ad

However, the Department for Infrastructure retains a central role, with responsibility for preparing planning policy and legislation, as well as monitoring and reporting on the performance of councils in delivering planning functions.

The report said that almost three-quarters of regionally significant and major planning applications processed between 2017-18 and 2019-20 were not completed within the statutory target of 30 weeks. More than half (56%) had taken more than a year to process, and 19% took longer than three years.

The report said the time taken to process major applications varies substantially between councils, with the average processing time for the slowest council more than three times that of the fastest council.

The report highlighted other notable variances between councils in their decision-making processes.

Hide Ad
Hide Ad

It said these include the extent to which planning decisions are delegated from elected representatives to professional planning officials, and how councils resolve enforcement cases where there are potential breaches of policies or planning conditions.

The report recognises the significant pressures that the planning system faces, with around 12,500 planning applications being processed each year since 2015.

It said that planning decisions have become increasingly complex, requiring more interaction with those who have specialist knowledge or skills, particularly with regard to assessing and managing environmental impacts.

While this requires more work for many applications, planning fees – the main source of income for the planning system – have not been adjusted year on year to keep pace with inflation.

Hide Ad
Hide Ad

The report said that, as a result, the planning system is increasingly financially unsustainable and the gap between the income generated from planning activities by councils and the cost of those activities has increased significantly.

These pressures have also contributed to slow progress in the creation of Local Development Plans (LDPs) by councils, the report added.

LDPs are intended to provide a 15-year framework to direct and control the scale and type of development in each council area.

However, seven years since the transfer of planning powers to local councils, none are complete and some LDPs remain at the early stages of development.

Hide Ad
Hide Ad

The lack of LDPs means planning decisions are not guided by long-term, up-to-date plans, the report said.

Mr Donnelly and Mrs Kane said: “The planning system can be a key enabler for the economic and social development of Northern Ireland, as well as playing an important role in protecting the environment.

“The focus of all those involved should be on ensuring it delivers its functions in an efficient, effective and financially sustainable way.

“The planning system in Northern Ireland is not currently operating as one system.

Hide Ad
Hide Ad

“Rather, there is a series of organisations that are not interacting well and not delivering an effective service.

“Addressing the issues identified in this report will be both a cultural and a practical challenge, demanding strong leadership.”

Among its other findings, the report also highlighted concerns over how the planning system is dealing with applications for developments that will produce ammonia emissions.

It said a lack of clear environmental guidance in regards to levels of ammonia emissions has resulted in significant uncertainty for planning authorities and applicants.