IN PICTURES: Take a look at how Ballycastle's £16.4m Leisure Centre is progressing 12 months on since work began

Causeway Coast and Glens Council has provided an update on the progress of Ballycastle’s new £16.4 million leisure centre – 12 months on since work began on the project.

Causeway Coast and Glens Council said on its website that since work began in February 2025 “significant progress has been made across various aspects of the project”.

"Initial works included the road works involving creation of a crossing point and filter lane on Quay Road itself along with site clearance work in preparation for the main construction.

"As the year has progressed the Swimming Pool tank has been excavated and constructed. The Leisure Centre Steelwork was completed in December which allows for the commencement of internal and external block work and roofing, while wider site works associated with pitch perimeter walking paths and drainage continue.

"The next twelve months will focus on completion of the Leisure Centre shell and the internal building fabric. Externally works will progress on the creation of a pump track, car park and a new inclusive play park.”

Mayor of the Borough, Cllr Oliver McMullan said: “I had the pleasure of visiting the site of the new Ballycastle Leisure Centre in December and was truly impressed by the progress being made.

" It’s fantastic to see the works advancing so well - this facility will be hugely important to the people of Ballycastle and surrounding area."

The new leisure facility has been jointly funded by Causeway Coast & Glens Borough Council and the UK Government and is set to be completed by November 2026.