A5 court ruling: Claim of 'monumental shambles' as stalled £1.7 billion road project given green light again
A court ruling overturning a decision to halt the A5 road project over Stormont’s climate change legislation is another milestone in a “monumental shambles” for everyone involved, the DUP has said.
There was mixed political reaction to a ruling by the Court of Appeal, with unionists welcoming the legal clarity provided, but raising concerns on behalf of landowners along the 58-mile road.


Nationalist politicians have called for the project to be progressed at speed, with the SDLP saying the ruling was “a major victory” for locals in West Tyrone.
Sinn Féin infrastructure minister Liz Kimmins says work on the delayed £1.7 billion road upgrade should begin as soon as possible – and it is her “top priority”.
Last month, a senior department official told a Stormont committee that £192.5m had been spent so far – with £36.8m spent in the last financial year alone.
There have been calls for decades for improvements to the route, amid concerns about the number of fatal accidents. However, the scheme had faced fresh delays over the implications of Stormont’s climate change act.
Green targets imposed under the law led a judge to rule it could not go ahead in its current form, as it would undermine the legal commitment to net zero. That has now been quashed.
Reacting to the latest news, the DUP says £200m has already been spent “without any new road being built” – describing the project as a “catalogue of failures”.
“Our communities want a safer A5. We know the devastating impact of lives lost on this road and the importance of better connections for businesses and the wider economy.
“Today’s ruling is a significant development. The Infrastructure Minister must now explain what it means for delivery and set out a clear, realistic timetable for everyone impacted on the route.
“£200 million has already been spent without any new road being built. Years of dither and delay have left affected landowners facing prolonged uncertainty. The project has been a shambles in stakeholder management with an almost total breakdown in relations between the Department and the landowners.
“Delivering this road and treating people fairly can go hand in hand but it requires a different approach. Farmers whose land and livelihoods are affected deserve proper compensation and workable arrangements. Some who had their land vested almost two years ago have still not been compensated for their property. Today’s judgment must now be followed by a credible plan on the ground.”
Ulster Unionist infrastructure spokesperson John Stewart welcomed the ruling’s clarity.
“Nobody should mistake today for a success story. Years were lost to a process that should never have been allowed to fail in the first place. The Public Accounts Committee warned the Department not to announce a decision until carbon budgets and a Climate Action Plan were in place. Two Sinn Féin Infrastructure Ministers pressed ahead regardless, and the High Court found that DAERA had given the Department no evidence-based assurance that the scheme could be reconciled with the law.
“The delay was not caused by the courts. It was caused by departments that did not do the work required of them, and the cost of that failure has fallen on everybody else.
“What the Minister must now set out is a realistic timetable, an honest figure for what this project will cost after years of inflation, and how it will be funded alongside everything else her Department is responsible for. She must also demonstrate that every pound of public money will be spent efficiently and effectively, with robust oversight to ensure there is no further waste”.
The SDLP’s Daniel McCrossan said the news “must finally clear the way for the long-awaited road to be built”.
The West Tyrone MLA said: “Above everything else, this is about saving lives. More than 50 people have died on the A5 since 2006. Too many families have buried loved ones, and too many communities have been left carrying that pain.
“There can be no more excuses and no more unnecessary delay. The Department and the Executive must move immediately to get work underway. The A5 is vital not only for road safety, but for the future of the West. It will connect our communities, strengthen our economy, attract investment and finally give this part of the island the modern infrastructure it has been denied for far too long”.
Sinn Féin MP for West Tyrone Órfhlaith Begley said the court ruling was “an important milestone for the A5 Western Transport Corridor project”.
“For far too long, families and communities have lived with the devastating consequences of a road that is not fit for purpose. Too many lives have been lost and too many people injured on the A5.
“These families have campaigned for change through the most unimaginable grief, and today we pay tribute to their courage and determination”.