Report reveals over £16m has been paid to contractors of the new Dundonald Ice Bowl
Over £16m has been paid to contractors of the new Dundonald Ice Bowl amid “likely changes” to its opening time-line.
A report to Lisburn and Castlereagh City Council’s (LCCC) communities committee, which has been seen by the Local Democracy Reporting Service (LDRS), shows an expected final hand over date of December 2027.
In 2023, councillors agreed to invest £52million at the leisure complex with £12.2million secured in ‘Levelling Up’ funding from the Westminster Government.
At that time a council report expected the new ice bowl to be open to the public in 2026.


This latest update report states: “A total of £16,670,423.63 has been paid to the contractor with full expenditure of the external funding (Levelling up Fund), of £12.2 million expended ahead of target.
“The current programme forecasts that the new facility will be constructed by March 2027 and staff training will then take place in the new building with full opening envisaged after training has taken place.
"The current facility will be demolished September 2027.”
The proposed new facility provides for an Olympic sized ice rink with spectator seating, 24 lane ten pin bowling experience, multi-function studios, restaurant/café, sensory and party rooms.
The facility will also see the introduction of a state-of-the-art gym with over 100 stations. This latest report to be presented to councillors further states: “The final handover of the site to council is programmed for December 2027, however with a programme of this scope and scale there is likely to be ongoing changes to the programme timeline.”