Stormont's £407,000 scaffolding bill for leaky roof - and repairs still haven't started

Stormont has spent £407,000 on scaffolding for its leaky roof, new figures have revealed, yet repairs still haven’t started.

The scaffolding has been in place since summer 2024, but a deal to get workmen on site was only being hammered out this month.

Stormont's parliament buildings is still waiting for repairs to its roof. Photo: Bernie Brownplaceholder image
Stormont's parliament buildings is still waiting for repairs to its roof. Photo: Bernie Brown

During a recent debate, MLA Trevor Clarke stated the cost of the scaffolding has been “published at £407,000”, adding officials thought it would be “less disruptive” to Stormont proceedings to leave it up, rather than dismantle and rebuild it as needed.

Mr Clarke was speaking on behalf of the Assembly Commission, which runs the buildings, staff and services at Stormont.

Trevor Clarke MLA has revealed the £407,000 cost of scaffolding that was built in 2024 and is still in place now, even though repairs haven't started.placeholder image
Trevor Clarke MLA has revealed the £407,000 cost of scaffolding that was built in 2024 and is still in place now, even though repairs haven't started.

It’s understood the cost breaks down as £245,000 on the scaffolding and £162,000 on professional fees.

The scaffolding was initially built at a cost of £74,000 for “investigative works”, Mr Clarke said, adding: “There was concern that, if the scaffolding were removed and later reinstalled, there would be criticism of that.

“The length of time that it has taken for the contract to be awarded has also been factored in. The [Assembly] Commission and those responsible therefore decided that it was best to keep the scaffolding in place for the foreseeable future until the work is done.”

Stating there had been “disruption to committees” while the scaffolding was erected in 2024, he said: “We would have had to endure that disruption to committees and to normal business again while it was removed, and it then would have had to be put back in place.

Ulster Unionist MLA Alan Chambers recalled disruption from the scaffolding being built, stating leaving it up is a better option. Photo: Kelvin Boyes/Press Eyeplaceholder image
Ulster Unionist MLA Alan Chambers recalled disruption from the scaffolding being built, stating leaving it up is a better option. Photo: Kelvin Boyes/Press Eye

“To allow the building to function, it was less disruptive to allow the scaffolding to remain in place.”

Repairs to the roof will be carried out in two phases, Mr Clarke said, and a tender for the first phase ended in January. Contracts were expected to be signed before the end of March, with the work to take six months to complete.

The DUP MLA also referred to a legal battle over repair work carried out in 2015, which concluded last year. Said Mr Clarke: “The assembly and the commission wish to move on from that.”

Ulster Unionist MLA Alan Chambers, who quizzed Mr Clarke over the issue in the Assembly, said rain has been leaking through the roof of parliament buildings, and officials are paying a monthly hire charge for the scaffolding that includes regular checks on the stability of its structure.

The Assembly Chamber in parliament buildings, Stormont.placeholder image
The Assembly Chamber in parliament buildings, Stormont.

He also stated the noise from building it had interfered with formal Stormont business in summer 2024, adding: “I recall sitting in committee rooms during the construction process when the volume meant windows had to be kept shut during periods of very hot weather, making the temperature in the room very uncomfortable.

“The noise continued to be disruptive despite windows being kept shut.”

Mr Chambers said he’s satisfied the current approach, while not ideal, is the best value for money of the options available.

“Given the explanation by the commission, I accept that the actions taken by them to date have been the best way forward in difficult and uncertain circumstances during this long-running saga.”

The Assembly was contacted for an update on the scaffolding and roof repairs, but has yet to reply.