£300m of major Belfast road projects stuck staring at red lights

Around £300m of major road projects in Northern Ireland’s capital city have broken down, with no sign of a green light for construction work starting.

That’s according to a new report from the body responsible for running them, Stormont’s Department for Infrastructure (DfI).

A computer-generated image showing what is meant to be the redeveloped York Street interchange.placeholder image
A computer-generated image showing what is meant to be the redeveloped York Street interchange.

It reveals that three huge construction schemes have either had handbrakes put on them, or are so short of money they’re unable to get into first gear.

The trio of stalled schemes are a massive reworking of the multiple-lane York Street interchange, a new Glider bus route connecting the city’s north and south, and a pedestrian and cycle bridge over the River Lagan.

New Glider bus routes in Belfast have been delayed due to a funding shortfall that has coffers at less than 40% of the cash needed to create them..placeholder image
New Glider bus routes in Belfast have been delayed due to a funding shortfall that has coffers at less than 40% of the cash needed to create them..

The projects are forecast to cost between £267.5m and £317.5m in total, though those figures include estimates of one project that are now more than a decade old and may no longer be realistic.

York Street’s crossroads links three of the busiest roads in Northern Ireland, Belfast’s Westlink plus the M2 and M3 motorways.

Traffic in the area is described by the DfI as a “major bottleneck” on the road network. The new interchange, stretching almost two miles, is supposed to build underpasses that will separate vehicles heading to the motorways from those staying in the city.

Back in 2015 it was priced at anywhere from £125m to £160m, though those old figures are currently under review.

A report detailing the delays in all three major projects is due to come up at Belfast City Hall last night. Photo: Iain Gray/News Letterplaceholder image
A report detailing the delays in all three major projects is due to come up at Belfast City Hall last night. Photo: Iain Gray/News Letter

According to DfI officials’ report, a contract to design the project was halted in 2017 by legal action, which resolved two years later.

Since 2020, however, the interchange has been stuck in a limbo of reviews, recommendations, consultancy and development work on recommendations, and “further engagement” commissioned by successive Infrastructure Ministers. In 2023 the scheme was placed on hold indefinitely.

Plans to boost Glider coverage would see a north-south route opened and an existing journey between the Titanic Quarter and the city centre extended to take in Queen’s University.

The additions need £124.5m to happen, but so far less than 40% of that amount has been assigned to the project.

A CGI image of the planned Lagan Pedestrian and Cycle Bridge in Belfast, put on hold by the Department for Infrastructure pending the outcome of a legal case it won last month.placeholder image
A CGI image of the planned Lagan Pedestrian and Cycle Bridge in Belfast, put on hold by the Department for Infrastructure pending the outcome of a legal case it won last month.

Initially intended to travel between Glengormley to the north of the city and Carryduff beyond Belfast’s southern boundary, a mix of budget pressures and congestion concerns have already seen that route scaled back.

Already heavily delayed, the north-south journey was last year put back again, its hoped-for start date shifting from 2030 to 2033 – which would mean it’ll begin running 15 years after the city’s east-west Glider route opened.

Although consultants were this year appointed to “progress the design phase”, state DfI officials, the total of £48m in the coffers for the new routes means that when it comes to actually getting Gliders going “a considerable shortfall remains”.

Stretching almost 470ft across the River Lagan, the planned pedestrian and cycle bridge is to link Ormeau Embankment with the redeveloped Gasworks area, now home to a host of large businesses.

It was one of a trio of schemes across Northern Ireland that Infrastructure Minister Liz Kimmins put on hold while she appealed a court’s decision to block a rebuild of the A5 road from Londonderry to the border at Co Monaghan.

The minister won that appeal last month, but there’s still no sign of a green light for the pedestrian bridge.

The DfI report is to be discussed by Belfast Council tonight.